Progress

The construction of the new building began in February 22, 2016. Followings are the estimated phases:

FebruaryMobilization
MarchDemolition
AprilFoundation
MayFoundation, concrete walls
June Concrete slab
July Structural steel
August Structure and framing
September Interior partitioning
October Exterior brick construction and stairways  
November Roofing
December Drywall installation
January Tile installation
February Interior finishing
March Site Work
April Parking lot
May Punch list
June-August Interior Decoration
September Completion